Steps to check Kavach Desktop Application Version

· The latest version that needs to be installed on system desktop is 3.6

· To check the version of the Kavach application, follow below steps:  Open the Kavach application on your NIC system > Click on about icon. > You will be able to see Kavach Authentication field, 3.5 is mentioned, which means application version is 3.6

Steps to enable IMAP using Kavach Desktop Application

1. Open the Kavach Application

2. On the left side panel click on third icon. Manage IMAP

3. Then click on Enable IMAP

Steps to configure path for Mailing Client (outlook , Mac and Thunderbird) in Kavach application

1. Open the Kavach Application and

2. Go to Setting Icon and then click on “Set Mail Path” to set the Outlook path

3. For Outlook path :- Select the any one of the below path as per your mail for setting Mail steup : 

a. OUTLOOK Path :- C:\ Program Files (x86)\Microsoft Office\Office14\outlook.exe 

b. MAC Path :- Application / Microsoft Outlook.app / Contents /Macos /Microsoft outlook 

c. Thunderbird Path :- /bin/Thunderbird

You will get message updated mail program path sucessfully.

Steps to configure Outlook for Kavach Application.

1. Open the Kavach Application.

2. At the left side of the application, click on Launch mail icon.

2. Open the Outlook application and create the account.

3. Click on Manually Configure & then click on Next

4. Click on Internet E-mail and then Next

5. Fill in the the required information which is hilighted in red BOX & then click on More Settings

6. Ensure all settings as per highlighted in red box

7. Click on Outgoing Server & check the “My outgoing server…” & then click on ok

8. Click on Next

9. You will see below screen, check Status is “Completed” & then click on “Close”

10. Click on Finish as below screen