DOP IT Project 2.0 | India Post IT Modernization Project 2.0 Governance Framework | Details of Post Office IT Modernization Project 2.0 | 2022

By Admin
0

DOP IT 2.0. Department of Post(DOP) IT Modernization Project 2.0. India Post IT Modernization Project 2.0 Governance Framework.

Cabinet has approved IT Project 2.0 on January 19, 2022. for an outlay of Rs 5785 Crore to be incurred for a period of eight years, from 2022-23 to 2029-30

Download IT Project 2.0 Documents in PDF

FINANCIAL OUTLAY

Rs.5785 crore for 8 years

NO DUAL STRUCTURE

Dual structure needs to be avoided and only single IPPB [India Post Payment Bank] structure to be used for banking, insurance and other financial needs

POSTAL & FINANCIAL

Core Postal Operations should be the domain of DoP and rest of operations should be merged with IPPB for providing a more integrated inclusive financial and other services to the customers.

STEERING COMMITTEE

empowered to modify the financial and physical parameters of the Project, which does not lead to substantial change in scope.

Transition Decisions

Decisions made by the Steering Committee of Ver 1.0 to transfer the contract management to IPPB for the following

DATACENTRE, NETWORK BANKING & INSURANCE 

The Data Center Facility Network Integrator after the after expiry of the current expiry of the current Banking, Insurance and AML contract w.e.f April 1, 2022 contract w.e.f April 1, 2022 post 29.08.2022 after the expiry of the current contract.


IPPB TRACKS (CABINET APPROVAL)

BANKING & INSURANCE

RURAL HARDWARE DEVICES

IT INFRA FRAUD & RISK MGT


DOP TRACKS (CABINET APPROVAL)

POSTAL & POINT OF SALE 

ACCOUNTING & BACK OFFICE MGT

FIELD NETWORK & POSTAL HARDWARE

PROJECT STEERING COMMITTEE

ROLE

1.To Sanction all projects under DoP IT 2.0 including total contract cost.

2.Revise the estimates under the overall outlay approved by the PIB.

3. Have the required degree of flexibility to modify the financial and physical parameters of the project, which does not lead to substantial change in the scope.

4. Monitor and review the implementation of the Project and ensure timely project completion.

TECHNOLOGY ADVISORY GROUPS

ROLE

1.Consists of eminent subject matter experts, Scholars, and industry representatives with domain and Technology expertise. The advice shall be taken independently on a subject matter basis with the relevant expert (s) as and when required.

2. It will work to give advice to DoP on Technical matters of respective fields like Artificial Intelligence, Machine Learning, Cloud Computing, Network optimisation, Solution architecture, design validation, Startup collaboration, New technology induction, and Industry and

3. The group shall be dynamically expanded/contracted on a need basis.

4.The Group shall be constituted by the Secretary (Posts). The Steering Committee members can also be part of the TAG.

PROJECT EVALUATION COMMITTEE

ROLE

1. Shall be responsible for meeting the goals of the Program, implementation roadmap, and Key Performance Indicators

2.Manage conflicts and resolve them. Shall approve the change request/deviations of the contracts / Scope as and when proposed by technology Division.

3. Shall scrutinise all deliverables and shall authorise the payment / release of funds to IPPB etc.


4.It will be chaired by Secretary Posts. Member (Technology), Respective chairman of PMC, ASFA, One representative from the field (CPMG/PMG) as members and DDG Technology as Convener.


5. The PEC shall invite the respective Committees, IPPB, NIC, e.t.c whose solutions are being reviewed.

PROJECT MANAGEMENT COMMITTEES

1.PMC shall be responsible for Business requirements, SRS, UAT, Training and Golive Management for both DoP and IPPB tracks.

2.For DoP Tracks, PMC additionally will also prepare EOI/ RFPs/ SLA/ MSA and do the vendor/product/technology selection.

3.PMC will be the complete owner of the track and shall ensure Rollout, Operations and Management of the application, and raise changes required.

4.PMC shall be responsible for the O&M phase. PMC shall have an effective monitoring team at CEPTs for SLA, and downtime

5.PMC shall assess & approve the new requirements and changes required in consultation with the Technology division.

6. The functional division head will chair the respective committee with concerned IFA, other functional heads of tracks, PMG/DPS from Field, and GM (CEPT) as members. Director (Tech)/ADG (Tech) will be Member Convenor.


CENTRE FOR EXCELLENCE IN POSTAL TECHNOLOGY

ROLE

1. Assisting the PMC in preparation of Scope of Work, EOI/RFPs, Bid evaluation, and Master Service Agreement.

2. The rollout of the solution in the field. Field testing (UAT), Pilot testing and deployment testing of any solution. Ensure the implementation of approved solutions.

3. Coordination with IPPB in output, transition, operational and Subject matter Support.

4.Documentation / Standard Operating Procedures (SOPs)

5.Monitoring of Deliverables and the SLA. Operation & Management Support.

MANAGEMENT OF IPPB TRACKS

ROLE

1. The functional requirements under the Program shall be prepared by the PMCs. The Technical architecture shall be prepared by Technology Division in consultation with the Technical Advisory Group & IPPB Technology team. (as required)

2.Approval of Steering Committee on Functional & Technical Requirements. Thereafter, IPPB to do RFP and Bid Process Management.

3.Post Solution Partner selection, IPPB shall enter into MoU with DoP for each track after the approval of Steering Committee and would lay down the roles, responsibilities, SLA, payment release terms, advance payments and milestones.


MANAGEMENT OF IPPB

1.After approval of MoU by the Steering Committee, the Project Evaluation PRODUCTION Committee shall be authorised to monitor the deliverable milestones, release the funds, and monitor the project.

2.In cases where there is a substantial change in scope, or there is a dispute, Shall the matter be referred to the Steering Committee by the Technology division.

3.IPPB shall submit to the Technology division, the performance report periodically along with a request for the release of funds after securing recommendations of PMC on the achievement of milestones.

4.Performance report shall be submitted to Project Evaluation Committee. PEC Shall sanction the release of funds to IPPB.


MANAGEMENT OF DOP TRACKS

ROLE

Onboarding of Solution Delivery Partners:

1.PMC shall prepare the functional requirements, the project estimated cost, EOI/ RFPs, and shall do the Technical/financial evaluation.

2. The Technology division shall take necessary financial and administrative approval from IFA concerned and the Steering Committee for the proposal of PMCs.

3. Technology Division does the bid opening management. PMC shall do bid evaluation and thereafter ensure the careful drafting of Master Service agreements.

4. The final selection of the Solution Delivery Partners(s) shall be approved by the Steering Committee.

5. The Steering Committee shall authorise the Project Evaluation Committee to monitor the deliverable milestones, and release the funds.



 

Click Here to Join Telegram Channel

Post a Comment

0Comments

Post a Comment (0)

#buttons=(Ok, Go it!) #days=(20)

Our website uses cookies to enhance your experience. Check Now
Ok, Go it!